FAQ’s on the BED Bond Item on the March 4 Ballot.
Why are Burlington voters being asked to approve a $39.6
million bond for BED?
BED
often bonds for projects that have a long-range benefit. This bond will include
several projects that will enhance our system and its reliability, allow us to
acquire renewable generation, reduce NOx emissions and provide greater rate
stability in the future. The bonds will be issued when needed to begin those
projects.
Will the bonds increase the electricity
rates of residents and businesses?
No.
The projects that the bonds will fund should generate enough revenue to cover
the cost of the debt service (principal and interest for the bond).
What are the projects?
There
are several.
*$10 million for power supply
acquisition. BED is planning to
contract for and possibly purchase generation. As our long-term power contracts
come to an end and we transition to the post fossil-fuel economy, we expect to
acquire more electricity from renewable instate generation, which is expected
to be more secure and stably priced over the long term than other sources.
*10.8 million for an
equity investment in VELCO. A higher share of equity by BED
in VELCO provides more security for BED
ratepayers, maintains our current VELCO ownership interest level, helps fund
major transmission upgrades within the state and provides a very high rate of
return (12.5 percent) on the investment.
*$5.4 million to pay for BED’s share of the East Avenue Loop Transmission Upgrade
project. This project will greatly enhance system reliability
within Burlington by providing a
looped feed between VELCO’s substation in Essex
and the East Avenue
substation and by providing BED with a
direct connection to McNeil power rather than paying to wheel this power over GMP’s lines.
*$4.5 million for a NOx
reduction unit at McNeil. Not only will this improve air quality
in the Burlington region by
reducing nitrogen oxide (NOx) emissions by over half and also reducing carbon
monoxide emissions, but, once completed, McNeil power will qualify in
high-value REC (Renewable Energy Credit) markets in Connecticut
and possibly Massachusetts. Under
current assumptions, this project has a two-year payback, after which Burlington
ratepayers will reap the monetary benefits of this investment. The air quality
benefits begin as soon as it is completed, which is scheduled for this fall.
$4.3 million to convert
more sections of the BED distribution system from
4 to 13.8 kilovolts. This conversion began several years ago and
is greatly improving reliability within Burlington.
It substantially reduces line losses, which saves ratepayer dollars. Once the
entire city is converted BED will not have
to maintain two separate distribution systems, which will save money.
$1.8 million to underground the BED distribution lines on the Waterfront.
There has long been a goal to remove overhead power lines along Burlington’s
beautiful Waterfront. This project will remove BED’s
distribution lines. GMP’s subtransmission lines will be
removed during a later phase.
$3 million for debt service reserve
costs. Setting aside this amount is required by the bonding authority
until the bond is paid off.
If the bond item is approved, does it mean
that all of these dollars will be drawn down immediately?
No.
This bond vote is to give BED the authority
to sell bonds up to the amount of $39.6 million. If any one of these projects
does not go forward, then BED will not sell
that portion of the bond.
Regarding the NOx reduction project at
McNeil, would this process involve the use of ammonia?
Yes,
the chemical process to achieve the NOx reduction uses ammonia, which acts
similarly to a catalytic converter. About one truck a week will transport
ammonia into Burlington. Unlike the
ammonia that is transported into Vermont
for agriculture, which is at 100 percent strength, this ammonia will be only at
a 19 percent strength.
Are there safeguards in place for storing
the ammonia?
Yes. The ammonia will be stored in a double-walled tank, and
an alarm will sound if the inside tank leaks.
On the outside chance there is a spill, McNeil
personnel would contact the emergency responders and clean up contractor to
have the spill cleaned up.