A. Summary
The offices and breakroom area within McNeil Station require a new HVAC installation.
Physical and other constraints favor ductless mini-split heat pump technology as the
solution. The installation will be multi-zone, with 5-10 heads likely installed for the optimal
solution. The compressor/condenser unit will be mounted on the office rooftop that is
directly above all spaces to be served. There is an existing 480V 3-phase service available.
B. Scope of Work
The scope of work for the vendor includes specification and procurement of hardware as well as all stages of installation to achieve a finished, turnkey system ready for immediate
use
| Milestone | Date |
| Release of Formal RFP | July 20, 2026 |
| Site Walkthrough | July 30, 2026 10am |
| Last Date to Submit Written Proposal | August 7, 2026 5 pm |
| Evaluation of Proposals | August 10, 2026 |
| Selection of contractor | August 11, 2026 |
| Date project may begin | August 12, 2026 |
| Date project must be completed | September 1, 2026 |