RFP Detail

Burlington Electric Department RFP System

RFP# 010-26 Cooling Tower Timber Replacement

RFP# 010-26

Deadline: August 8, 2025 5:00 pm

  1. Summary

The existing timbers of the cooling tower require selective replacement. This project will replace a portion of existing timbers during a maintenance outage that is already scheduled for October 18th through November 9th, 2025.

 

  1. Scope of Work

There are two scopes of work to bid on. After evaluation of all bids, BED will select a single bid and its associated scope of work.

 

Scope of work #1

Replace 50% of timbers in the cooling tower structure with Douglas Fir CCA pressure treated lumber. Quantities and dimensions of lumber for scope of work #1:

  • 250 total 2”x4”x20’
  • 250 total 2”x6”x20’
  • 150 total 4”x4”x20’
  • 150 total 4”x4”x10’

 

Scope of work #2

Replace 25% of timbers in the cooling tower structure with Douglas Fir CCA pressure treated lumber. Quantities and dimensions of lumber for scope of work #2:

  • 125 total 2”x4”x20’
  • 125 total 2”x6”x20’
  • 75 total 4”x4”x20’
  • 75 total 4”x4”x10’

 

The following requirements apply to both scopes of work:

  1. Removal and reinstallation of cooling tower fill media as necessary
  2. Removal and reinstallation of cooling tower components as necessary
  3. Clean up of debris
  4. Work must be 100% complete in the available time window October 18th through November 5, 2025. Pre-staging of materials prior to these dates may be acceptable and coordinated with BED.
  5. Material for the project will be supplied by the bidder
  6. All equipment rentals will be supplied by the bidder.
  7. Disposal of any chemicals used will be done by the bidder.
  8. Clean up and removal of all debris

Proposed Schedule

Milestone

Date  

Release of Formal RFP

7/16/2025

Site Walkthrough (Not required)

-----------

Last Date to Submit Written Proposal

8/8/2025 5 PM

Evaluation of Proposals

8/29/2025

Selection of contractor

8/29/2025

Date project may begin

10/20/2025

Date project must be completed

11/05/2025

 

 

Documents

Submit Your Proposal

RFP Submission