RFP# 011-27 McNeil Station SCADA Upgrade

RFP# 011-27

Deadline: October 15, 2026 5:00 pm

The City of Burlington Electric Department invites proposals for development, installation, and integration work for a new SCADA (Supervisory Control And Data Acquisition) system built on the Inductive Automation Ignition platform for control of the McNeil Generating Station power plant.

Milestone

Date  

Release of Formal RFP

Friday, August 28, 2026

Site Walkthrough

Tuesday, September 22, 2026 at 10:00AM EST

Last Date to Submit Written Proposal

Wednesday, October 14, 2026 at 5:00PM EST

 Evaluation of Proposals

Thursday, October 15, 2026

Selection of contractor

By Tuesday, October 20, 2026

Date project may begin

 After contractor has been selected

Date project must be completed

The project should be ready to be commissioned in April 2027.