Burlington Electric Department RFP System
RFP# 011-27 McNeil Station SCADA Upgrade
RFP# 011-27
Deadline: October 15, 2026 5:00 pm
The City of Burlington Electric Department invites proposals for development, installation, and integration work for a new SCADA (Supervisory Control And Data Acquisition) system built on the Inductive Automation Ignition platform for control of the McNeil Generating Station power plant.
|
Milestone |
Date |
|
Release of Formal RFP |
Friday, August 28, 2026 |
|
Site Walkthrough |
Tuesday, September 22, 2026 at 10:00AM EST |
|
Last Date to Submit Written Proposal |
Wednesday, October 14, 2026 at 5:00PM EST |
|
Evaluation of Proposals |
Thursday, October 15, 2026 |
|
Selection of contractor |
By Tuesday, October 20, 2026 |
|
Date project may begin |
After contractor has been selected |
|
Date project must be completed |
The project should be ready to be commissioned in April 2027. |
Documents
Submit Your Proposal