McNeil Station ESP Field Rebuild RFP#051-26 Rev 1.20.26
RFP# 051-26
Deadline: February 20, 2026 5:00 pm
Burlington Electric Department would like to receive fixed-cost proposals for the rebuild of one electrostatic precipitator field per the scope below.
Please submit your proposal to provide materials and labor during the four-week planned outage for maintenance work on the electrostatic precipitator at the McNeil Generating Station in accordance with the following specifications by February 20, 2026.
- Facility Description - The McNeil Generating Station is a 50 MWe steam driven wood fired electric generating station located in the City of Burlington, Vermont. To comply with air quality standards, the station operates an electrostatic precipitator (ESP) when firing wood. The ESP is a GEESI (Buell) Model BA1.2x52K4443-6.4P with 30' plates. The collecting plates and emitting wires were replaced in 1997 by BHA. The BHA drawings show what was installed and needs to be replaced in this project.
- Contractor's Supply - The Contractor shall supply both materials and installation labor with supervision for the outage work specified below. The Contractor shall provide approved drawings of all materials to be installed no later than four (4) weeks prior to delivery of the materials.
|
Milestone |
Date |
|
Release of Formal RFP |
January 14, 2026 |
|
Site walkthrough |
January 29, 2026 10 am est |
|
Last Date to Submit Written Proposal |
February 20, 2026 5pm est. |
|
Evaluation of Proposals |
February 23, 2026 |
|
Selection of contractor |
February 23, 2026 |
|
Date Project can begin |
April 25, 2026 |
|
Project must be completed by |
May 22, 2026 |
Question:
Can the BHA drawings be provided or should we use the Precipitator Services Group drawings from 2010 that were included in the RFQ?
Answer:
Has been added to the RFP last drawing in the drawing section.